Satellite analysis points to diversion works at China’s Medog hydropower site upstream of Arunachal
Satellite imagery analysed by Indian geospatial intelligence firm EarthSense Labs indicates significant land clearance, road construction and river diversion-related activity at Mainling, the site where China formally launched its Medog hydropower project in July 2025. The findings provide a closer picture of construction along the Tibetan stretch of the Yarlung Tsangpo, which enters Arunachal Pradesh as the Siang and flows through Assam as the Brahmaputra.
China's proposed project on the lower Yarlung Tsangpo is planned as a cascade of five hydropower stations, with an estimated investment of 1.2 trillion yuan (approximately US$168 billion) and a proposed installed capacity of 60,000 megawatts (60 GW). Once completed, it would be the world's largest hydropower project, with three times the installed capacity of China's Three Gorges Dam.
Beijing has maintained that the project will generate electricity for Tibet and other parts of China without significantly affecting downstream water supplies.
Satellite imagery reveals construction progress
In its 18-page EarthSense Discovery Report, titled Building at the Great Bend: Monitoring China's 60 GW Medog Dam Project, EarthSense Labs presents a satellite-based assessment of construction activities at three key locations associated with the proposed project.
The report compares satellite imagery from different years to identify changes in land use, construction infrastructure and development around the proposed dam and tunnel locations.
At Mainling, imagery dated July 11, 2025, shows villages and agricultural fields in the area before the project's groundbreaking ceremony on July 25, 2025. Subsequent imagery from December 4, 2025, and August 10, 2026, indicates extensive site clearance, removal of agricultural land, excavation and the development of new infrastructure.
According to the assessment, villages and agricultural fields on the southern bank were cleared, while new roads, concrete structures and temporary buildings appeared on the northern bank.
By August 2026, satellite imagery also showed river diversion-related works, extensive earthmoving and excavation activities, along with offices and other construction infrastructure.
The report identifies the progression from site clearance and earthworks to river diversion activity as a significant development at the Mainling site.
EarthSense identifies other possible dam locations
Dr. Nirdesh Kumar Sharma, Co-Founder and CEO of EarthSense Labs, a deep-tech company incubated at the Foundation for Innovation and Technology Transfer (FITT), IIT Delhi, said the company's assessment also identified Pai and Xirang as two other likely dam locations.
According to Dr Sharma, the company used satellite imagery and tender records to identify these locations and assess the possible configuration of the hydropower infrastructure.
The proposed arrangement would involve tunnels beneath the Namcha Barwa massif to divert water through a section of the Great Bend of the Yarlung Tsangpo. While China has publicly identified Mainling as the groundbreaking site, the proposed roles of Pai and Xirang and the tunnel alignment are part of EarthSense Labs' assessment.
The report identifies Mainling as the upstream high-dam location, Pai Town as a possible lower-dam location and the area near Medog, close to the India-China border, as the downstream tunnel outlet and associated construction zone.
At the possible Pai Town low-dam location, however, EarthSense found no conclusive evidence of structural dam construction in satellite imagery up to October 2026. The assessment suggests that work may be progressing from the lower tunnel end instead.
Major infrastructure development near the border
The assessment documents substantial infrastructure development around the proposed tunnel outlet near the India-China border, downstream of Medog County.
A comparison of satellite imagery from 2021 and 2024 shows the emergence of new bridges, roads, machinery, industrial buildings and a concrete batching plant.
The report traces the area's transformation to earlier years. In 2018, the location had a small community, although road construction along the river had already begun. Further groundwork was visible during 2019–2020, followed by the development of residential and industrial buildings by 2021.
EarthSense estimates that around 30–35 additional residential and industrial buildings appeared during 2023–2024.
One significant development identified is a concrete batching plant established between April and August 2024. Satellite images show that an area previously covered by forest had been cleared and converted into an industrial facility. By 2024, the site also contained several industrial buildings and around 15 small and large trucks and vehicles.
The report further documents a bridge whose construction began in 2020 and was completed by 2021. Office and industrial buildings subsequently appeared alongside it.
Another comparison of satellite imagery from March 2023 and May 2024 reveals extensive road construction leading towards the river, with much of the development taking place during 2023–2024.
Potential downstream implications for Arunachal and Assam
The scale and location of the proposed project have implications for communities downstream in Arunachal Pradesh and Assam, particularly because the Yarlung Tsangpo eventually becomes the Brahmaputra, a major river system supporting millions of people.
EarthSense Labs has highlighted the potential influence of reservoir filling and water releases for electricity generation on downstream river flows, particularly during the dry season.
The cascade of hydropower stations could also affect the movement of sediment carried by the river towards the Brahmaputra floodplains.
However, the extent of any downstream changes would depend on the project's storage capacity, operating arrangements, water-release schedules and the contribution of tributaries further downstream.
The region has previously experienced sudden transboundary flood events. In 2000, a massive landslide blocked the Yigong River in Tibet, a tributary of the Yarlung Tsangpo. The subsequent collapse of the natural barrier triggered a major flood that affected Arunachal Pradesh and the Brahmaputra basin.
Concerns over cross-border hydrological information-sharing have also persisted. India told Parliament in 2025 that China had suspended the supply of Brahmaputra hydrological data in June 2023, following the expiry of the bilateral agreement, and that New Delhi had sought its resumption.
Opposition to Arunachal's proposed Siang dam
The satellite findings emerge amid continuing opposition to the proposed 11,200-MW Siang Upper Multipurpose Project in Arunachal Pradesh.
Survey and drilling activities associated with the project's pre-feasibility study have drawn protests from sections of the Indigenous Adi community, who have expressed concerns over displacement, loss of ancestral land and threats to traditional livelihoods.
The Siang Indigenous Farmers' Forum has alleged that affected landowners were excluded from consultations. Protests in Pasighat turned violent on October 23.
The state government's position is that a reservoir on the Siang could help manage sudden changes in water flow originating upstream.
The proposed Indian project has therefore become part of a wider debate over water security, development, indigenous rights and the management of the Brahmaputra river system.
The EarthSense Labs assessment provides a detailed satellite-based record of infrastructure development taking place upstream. However, the actual downstream consequences of China's project will depend on its eventual design, storage capacity and operational arrangements.
For communities along the Siang and Brahmaputra, questions surrounding upstream water management, timely hydrological information and the protection of local livelihoods remain significant.